Arts Elevator Addition - In Progress
Overview
The Arts Elevator Addition project improves connectivity within the Arts Building by introducing a new elevator and tower, a dedicated control room, and corridor
connections linking the tower to the existing building. Construction began in April
2025 and is currently underway, with excavation and foundation work in progress. The purpose of the elevator addition is to provide additional access and to ensure
functional circulation throughout the building.
The project is scheduled for completion in Spring 2026.
Please check back for periodic updates.
Project Manager:
Al Krisinkas
Project Budget:
$4,778,000
Funding Source:
The Arts Elevator Addition project is funded primarily by State Revenue Bonds, supplemented by a campus contribution.